At a sprawling manufacturing complex here, hundreds of Chinese laborers are 
now completing work on the San 
Francisco-Oakland Bay Bridge. 

Next month, the last four of more than two dozen giant steel modules — each with a roadbed segment about half the size of a 

football field — will be loaded onto a huge ship and transported 6,500 miles to Oakland. There, they will be assembled to fit
 
into the eastern span of the new Bay Bridge. 

The project is part of China’s continual move up the global economic value chain — from cheap toys to Apple iPads to 

commercial jetliners — as it aims to become the world’s civil engineer. 

The assembly work in California, and the pouring of the concrete road surface, will be done by Americans. But construction of 

the bridge decks and the materials that went into them are a Made in China affair. California officials say the state saved 

hundreds of millions of dollars by turning to China. 

“They’ve produced a pretty impressive bridge for us,” Tony Anziano, a program manager at the California Department of 

Transportation, said a few weeks ago. He was touring the 1.2-square-mile manufacturing site that the Chinese company 

created to do the bridge work. “Four years ago, there were just steel plates here and lots of orange groves.” 

On the reputation of showcase projects like Beijing’s Olympic-size airport terminal and the mammoth hydroelectric Three 

Gorges Dam, Chinese companies have been hired to build copper mines in the Congo, high-speed rail lines in Brazil and huge 

apartment complexes in Saudi Arabia. 

In New York City alone, Chinese companies have won contracts to help renovate the subway system, refurbish the Alexander 

Hamilton Bridge over the Harlem River and build a new Metro-North train platform near Yankee Stadium. As with the Bay 

Bridge, American union labor would carry out most of the work done on United States soil. 

American steelworker unions have disparaged the Bay Bridge contract by accusing the state of California of sending good jobs 

overseas and settling for what they deride as poor-quality Chinese steel. Industry groups in the United States and other 

countries have raised questions about the safety and quality of Chinese workmanship on such projects. Indeed, China has had 

quality control problems ranging from tainted milk to poorly built schools. 

But executives and officials who have awarded the various Chinese contracts say their audits have convinced them of the 

projects’ engineering integrity. And they note that with the full financial force of the Chinese government behind its 

infrastructure companies, the monumental scale of the work, and the prices bid, are hard for private industry elsewhere to 

beat. 

The new Bay Bridge, expected to open to traffic in 2013, will replace a structure that has never been quite the same since the 

1989 Bay Area earthquake. At $7.2 billion, it will be one of the most expensive structures ever built. But California officials 

estimate that they will save at least $400 million by having so much of the work done in China. (California issued bonds to 

finance the project, and will look to recoup the cost through tolls.) 

California authorities say they had little choice but to rebuild major sections of the bridge, despite repairs made after the 

earthquake caused a section of the eastern span to collapse onto the lower deck. Seismic safety testing persuaded the state 

that much of the bridge needed to be overhauled and made more quake-resistant. 

Eventually, the California Department of Transportation decided to revamp the western span of the bridge (which connects 

San Francisco to Yerba Buena Island) and replace the 2.2-mile eastern span (which links Yerba Buena to Oakland). 

On the eastern span, officials decided to build a suspension bridge with a complex design. The span will have a single, 

525-foot tower, anchored to bedrock and supported by a single, enormous steel-wire cable that threads through the 

suspension bridge. 

“We wanted something strong and secure, but we also wanted something iconic,” said Bart Ney, a transportation department 

spokesman. 

A joint venture between two American companies, American Bridge and Fluor Enterprises, won the prime contract for the 

project in early 2006. Their bid specified getting much of the fabricated steel from overseas, to save money. 

California decided not to apply for federal funding for the project because the “Buy America” provisos would probably have 

required purchasing more expensive steel and fabrication from United States manufacturers. 

China, the world’s biggest steel maker, was the front-runner, particularly because it has dominated bridge building for the 

last decade. Several years ago, Shanghai opened a 20-mile sea bridge; the country is now planning a much longer one near 

Hong Kong. 

The selection of the state-owned Shanghai Zhenhua Heavy Industries Company was a surprise, though, because the company 

made port cranes and had no bridge building experience. 

But California officials and executives at American Bridge said Zhenhua’s advantages included its huge steel fabrication 

facilities, its large low-cost work force and its solid finances. (The company even had its own port and ships.) 

“I don’t think the U.S. fabrication industry could put a project like this together,” Brian A. Petersen, project director for the 

American Bridge/Fluor Enterprises joint venture, said in a telephone interview. “Most U.S. companies don’t have these types 

of warehouses, equipment or the cash flow. The Chinese load the ships, and it’s their ships that deliver to our piers.” 

Despite the American union complaints, former California Gov. Arnold Schwarzenegger, a Republican, strongly backed the 

project and even visited Zhenhua’s plant last September, praising “the workers that are building our Bay Bridge.” 

Zhenhua put 3,000 employees to work on the project: steel-cutters, welders, polishers and engineers. The company built the 

main bridge tower, which was shipped in mid-2009, and a total of 28 bridge decks — the massive triangular steel structures 

that will serve as the roadway platform. 

Pan Zhongwang, a 55-year-old steel polisher, is a typical Zhenhua worker. He arrives at 7 a.m. and leaves at 11 p.m., often 

working seven days a week. He lives in a company dorm and earns about $12 a day. 

“It used to be $9 a day, now it’s $12,” he said Wednesday morning, while polishing one of the decks for the new Bay Bridge. 

“Everything is getting more expensive. They should raise our pay.” 

To ensure the bridge meets safety standards, 250 employees and consultants working for the state of California and American 

Bridge/Fluor also took up residence in Shanghai. 

Asked about reports that some American labor groups had blocked bridge shipments from arriving in Oakland, Mr. Anziano 

dismissed those as confused. 

“That was not about China,” he said. “It was a disagreement between unions about which had jurisdiction and who had the 

right to unload a shipment. That was resolved.” 